In the same way railroad switches direct trains in this direction or that, open a track here and close another there ... the ITER switchyard will dispatch electricity from the newly built 400kV double power line to seven transformers connected to the installations. Construction of these transformers—four procured by the United-States and three by China—should begin in 2014.

The power that will be supplied to ITER is channelled from a giant switchyard located to the west of Avignon in Tavel (famous for its rosé wine...). From there, electricity travels 125 kilometres to a large substation in the hamlet of Boutre, close to village of Ginasservis some three kilometres south-east of the ITER platform.

The 400 kV "Boutre-Tavel" power line is an essential link in the interconnected European grid. It supplies electricity to a vast area of south-eastern France and, since the construction of a derivation in the late 1980s, also to the CEA-Euratom tokamak Tore Supra.

In terms of instantaneous electricity consumption, tokamaks are gluttonous machines. Tore Supra requires up to 100 MW of power for every plasma shot; as a much larger and more powerful machine, ITER will demand an average of three to four times more.

The anticipated needs of ITER have led to an extension and a reinforcement of the Tore Supra derivation: like "Boutre-Tavel," the new power highway delivers 400kV by way of two distinct and redundant power lines.

ITER of course will not use the power lines' total capacity. Plasma pulses will indeed need hundreds of megawatts, but the daily operation of auxiliary plant systems will require much less.

"The ITER switchyard guarantees maximum flexibility, both for ITER and for the Réseau de Transport d'électricité (RTE) that operates the Boutre-Tavel power line," explains Joël Hourtoule, section leader for ITER's Steady State Electrical Network Section.

Tension variation on a 400kV power line must remain limited to 3 percent. In order to remain within this tolerance, ITER operations must be closely coordinated with RTE dispatching.

"ITER will provide RTE with annual, monthly and weekly planning schedules. Prior to each plasma shot, ITER will send a signal to the RTE Regional Dispatch Centre in Marseille and receive back an authorization to proceed — or not. This procedure needs to be finalized prior to ITER's operational phase."

Source: ITERnewsline

HiPER fusionForEnergyLogo logo EUROfusion iter Laserlab Europe Fusenet European Commission Logo MEiN

Research projects carried out at the IPPLM are funded by the Polish Ministry of Education and Science, the National Science Centre and by the European Commission within the framework of EUROfusion Consortium under grant agreement No 101052200. Financial support comes also from the International Atomic Energy Agency, European Space Agency and LaserLab Consortium as well as from the Fusion for Energy Agency.